EDC-managed capital project (SBS / FMS agency 801); Checkbook-joined spend.
Budget
$169M
Spent to date
$169M
Remaining
$0
Budget used
100%
4 phases
| # | Phase | Timeline | Status |
|---|
| Budget / spent |
|---|
| 1 | Design | Jan 1, 2023 – Jun 30, 2024 | Complete | $25.3M / $25.3M100% |
| 2 | Procurement | Jan 1, 2024 – Jun 30, 2025 | Complete | $16.9M / $16.9M100% |
| 3 | Construction | Jan 1, 2025 – Jun 30, 2026 | Complete | $110M / $110M100% |
| 4 | Closeout | Jan 1, 2026 – Jun 30, 2027 | Complete | $16.9M / $16.9M100% |
No inspection deficiencies bundled into this project
This project isn't tied to inspection deficiencies. Condition-driven candidates bundle their priced backlog here.